Answer:
$85.56 per unit
Step-by-step explanation:
Assembly = $498,520 / 44,000 Machine hours
Assembly = $11.33 per machine hour
Processing orders = $54,263 / 1,100 Orders
Processing orders = $49.33 per processing orders
Inspection = $77,589 / 1,100 Inspections
Inspection = $70.54 per inspections
Total Overhead Costs = [990*$11.33] + [70*$49.33] + [20*$70.54]
Total Overhead Costs = $11,217 + $3,453 + $1,411
Total Overhead Costs = $16,081
Overhead Cost per unit = Total Overhead cost / Number of units produced
Overhead Cost per unit = $16,081 / 430 Units
Overhead Cost per unit = $37.37 Per unit
Step-3, Average cost of product L19B
Unit cost of product L19B = Direct Material cost per unit + Direct Labor cost per unit + Overhead costs per unit
Unit cost of product L19B = $37.74 + $10.45 + $37.37
Unit cost of product L19B = $85.56 per unit