21 men can complete a piece of work in 30 days. How many more men should employed to finish the work in 18 days​

1 Answer

1 vote

Explanation:

21 men * 30 days = 630 man days needed to get the job done

630 man days / 18 days = 35 men needed

that would be 14 MORE needed