Answer:
$6177
Step-by-step explanation:
Calculation to determine what The total cost for the job on its job cost sheet would be
TOTAL COST
Direct materials $2,117
Direct labor (34 direct labor-hours × $14 per direct labor-hour) $476
Overhead (224 machine-hours × $16 per machine-hour) $3584
Total manufacturing cost
$6177
Therefore The total cost for the job on its job cost sheet would be:$6177