Answer:
Issue: Whether Ecclestone Signature Homes of Palm Beach, LLC (ESH) breached its contract with Ge Lin by failing to complete the construction of a luxury home in a timely manner.
Rule: Under Florida law, a party is liable for breach of contract if they fail to perform their contractual obligations in a timely manner. The non-breaching party may be entitled to damages equal to the losses they incurred as a result of the breach.
Analysis: In this case, Ge Lin hired ESH to construct a luxury home. The contract specified a completion date of June 30, 2018. However, ESH failed to complete the construction by the deadline, and the project was not completed until six months later. As a result, Ge Lin incurred additional expenses and lost rental income.
ESH breached its contractual obligation to complete the construction by the deadline. Ge Lin suffered damages as a result of the breach. Therefore, ESH is liable for breach of contract.
Conclusion: ESH breached its contract with Ge Lin by failing to complete the construction of the luxury home by the specified deadline. Ge Lin is entitled to damages equal to the losses incurred as a result of the breach.