127k views
4 votes
The complete question is ABC Co has a target debt ratio of 40% and it keeps this target. The cost of equity is 10% and the cost of debt is 4%. It is considering expanding its business and requires $1 million investment. After expansion, ABC expects additional free cash flows of $0.2 million per year in perpetuity. ABC decides to issue equity to finance this expansion. The equity issuance cost is 5%. The corporate tax rate is 30%. Assume that ABC will maintain the target debt ratio. What's the NPV of the expansion project?

User Zoe Gagnon
by
8.3k points

1 Answer

0 votes

Step-by-step explanation:

To calculate the NPV (Net Present Value) of the expansion project, we need to determine the cash flows associated with the project and discount them to their present values.

Given information:

Target debt ratio = 40%

Cost of equity (Ke) = 10%

Cost of debt (Kd) = 4%

Equity issuance cost = 5%

Tax rate = 30%

Investment required = $1 million

Additional free cash flows per year = $0.2 million

Step 1: Calculate the weighted average cost of capital (WACC).

WACC is the weighted average of the cost of equity and the after-tax cost of debt, considering the target debt ratio.

Weight of equity (We) = 1 - Target debt ratio = 1 - 0.40 = 0.60

Weight of debt (Wd) = Target debt ratio = 0.40

WACC = (We * Ke) + (Wd * Kd * (1 - Tax rate))

WACC = (0.60 * 0.10) + (0.40 * 0.04 * (1 - 0.30))

WACC = 0.06 + 0.0112

WACC = 0.0712 = 7.12%

Step 2: Calculate the present value of the additional free cash flows.

Since the additional free cash flows are expected to continue indefinitely, we can use the perpetuity formula.

PV = CF / r

PV = $0.2 million / 0.0712

PV ≈ $2.81 million

Step 3: Calculate the present value of the investment required.

The investment required is $1 million.

PV = CF / r

PV = -$1 million / 0.0712

PV ≈ -$14.04 million (negative sign indicates cash outflow)

Step 4: Calculate the net present value (NPV).

NPV = PV of cash inflows - PV of cash outflows

NPV = $2.81 million - $14.04 million

NPV ≈ -$11.23 million

Therefore, the NPV of the expansion project is approximately -$11.23 million. This indicates a negative NPV, suggesting that the project may not be financially viable or profitable given the specified assumptions and costs.

User Nick Coons
by
7.6k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.