At the beginning of the year, X Company expected to produce 3,100 units of its only product. Its estimate of fixed overhead was $13,000, and its estimate of variable overhead per unit was $6.97. At the end of the year, 2,800 units were actually produced, with actual total overhead cost of $29,891. What was X Company's total overhead flexible budget varlance for the year [a positive number means a favorable variance; a negative number means an unfavorable variance]?

User Locorecto
by
7.5k points

1 Answer

3 votes

To calculate the total overhead flexible budget variance, we need to compare the actual overhead costs with the budgeted overhead costs.

The budgeted overhead costs can be calculated using the formula:

Budgeted Overhead Costs = Fixed Overhead + (Variable Overhead per Unit × Budgeted Units)

Given:

Fixed Overhead = $13,000

Variable Overhead per Unit = $6.97

Budgeted Units = 3,100 units

Budgeted Overhead Costs = $13,000 + ($6.97 × 3,100)

Budgeted Overhead Costs = $13,000 + $21,587

Budgeted Overhead Costs = $34,587

Now, we can calculate the total overhead flexible budget variance using the formula:

Total Overhead Flexible Budget Variance = Budgeted Overhead Costs - Actual Overhead Costs

Given:

Actual Overhead Costs = $29,891

Total Overhead Flexible Budget Variance = $34,587 - $29,891

Total Overhead Flexible Budget Variance = $4,696

Therefore, X Company's total overhead flexible budget variance for the year is $4,696 (a positive number, indicating a favorable variance).