Answer:
8 Days
Explanation:
The assignment can be finished by Binny and Ravi in 8 days.
GIVEN: Binny can complete a project in 24 days. Two times as quickly as Binny, Ravi works.
TO FIND: If they both work together, how many days they will complete the project?
SOLUTION:
The aforesaid issue is easily resolved by doing the following:
We are informed that Binny has 24 days to complete the work.
Binny's day of work equals 1/24
We now know that Ravi works twice as quickly as Binny.
As a result, Ravi needs 12 days to complete the work.
One day's work for Ravi equals one-twelfth.
1-day work of both Ravi and Binny = 1/12 + 1/24
= 2+1/24
= 3/24
= 1/8
Ravi and Binny can complete the task in 8 days.