you have developed the schedule for your project and want to assess the risk. which model will you chose for this?

User SgtHale
by
8.6k points

1 Answer

1 vote

Final answer:

To assess project schedule risk, Monte Carlo simulation, Decision Tree Analysis, or Qualitative Risk Analysis can be chosen. Monte Carlo simulation offers probabilistic outcomes; Decision Tree visualizes outcomes and paths; Qualitative Risk Analysis assesses impact and likelihood in a subjective manner.

Step-by-step explanation:

If you have developed a schedule for your project and want to assess the risk, a variety of models could be chosen depending on the specifics of the project, available information, and the nature of risks you want to analyze. One effective approach is to use a Monte Carlo simulation, which can help in assessing the risk by providing a range of possible outcomes based on probability distributions.

Another option could be the Decision Tree Analysis, which helps in visualizing the different possible outcomes and the paths that lead to them. It can incorporate the likelihood of risks and the impacts if they were to occur. Furthermore, a Qualitative Risk Analysis can be utilized to evaluate the impact and likelihood of risks in a more subjective manner.

When considering which model to choose, you should analyze the costs and benefits; taking into account the asymmetric risk presented in a plan (for instance, the catastrophic downside of a risk being realized versus the non-ideal but less severe consequences of a precaution deemed unnecessary later).