Final answer:
The company needs to hire 3640 temporary staff.
Step-by-step explanation:
To find out how many temporary staff Company A needs to hire, we first need to calculate the total number of t-shirts the full-time staff can produce in the given time period.
Given:
- 5 full-time staff
- Each staff person can make 5 t-shirts per hour
- The company needs to make 35,000 t-shirts in the first 12 weeks of the year
- Assume a 40-hour work week
- 60 days per season
- A 2080-hour work year
Step 1: Calculate the total number of hours available for production in the first 12 weeks:
12 weeks x 7 days/week x 40 hours/day = 3360 hours
Step 2: Calculate the total number of t-shirts the full-time staff can produce:
5 t-shirts/hour x 3360 hours = 16,800 t-shirts
Step 3: Calculate the number of t-shirts the temporary staff needs to produce:
35,000 t-shirts - 16,800 t-shirts = 18,200 t-shirts
Step 4: Calculate the number of temporary staff needed:
Since each full-time staff can make 5 t-shirts per hour, we divide the number of t-shirts needed by the number of t-shirts produced per hour:
18,200 t-shirts / 5 t-shirts per hour = 3640 hours
Therefore, Company A needs to hire 3640 temporary staff to meet their production target.