Final answer:
To calculate the NPV of the project, you need to calculate the net cash flows for each year and discount them using the discount rate. The NPV for this project is $272,494.77.
Step-by-step explanation:
To calculate the NPV of the project, we need to calculate the net cash flows for each year and discount them using the discount rate. The net cash flow for each year is the difference between the savings in pretax operating costs and the depreciation expense. The savings in pretax operating costs per year is $207,000 and the depreciation expense per year is ($715,000 - $97,000) / 5 = $123,600. Therefore, the net cash flow for each year is $207,000 - $123,600 = $83,400. To calculate the NPV, we discount these cash flows using the discount rate of 8%. The NPV is calculated as follows:
Year 1: $83,400 / (1+0.08)^1 = $76,944.44
Year 2: $83,400 / (1+0.08)^2 = $71,224.72
Year 3: $83,400 / (1+0.08)^3 = $65,919.81
Year 4: $83,400 / (1+0.08)^4 = $60,993.33
Year 5: $83,400 / (1+0.08)^5 = $56,411.47
Finally, we sum up the discounted cash flows and subtract the initial investment in net working capital of $59,000 to get the NPV:
NPV = $76,944.44 + $71,224.72 + $65,919.81 + $60,993.33 + $56,411.47 - $59,000 = $272,494.77.