Final answer:
To compute the net present value (NPV) of Project A and Project B, we need to calculate the present value of each cash flow and subtract the initial investment. The NPV of Project A is $6,173.94 and the NPV of Project B is $5,953.72. The company should accept Project A.
Step-by-step explanation:
To compute the net present value (NPV) of Project A and Project B, we need to calculate the present value of each cash flow and subtract the initial investment. The present value of each cash flow is computed by dividing the cash flow by (1 + discount rate) raised to the power of the respective year. Then, we sum up the present values and subtract the initial investment to get the NPV.
Here are the calculations:
Project A: NPV = (-$100,000) + ($30,000 / (1 + 0.14)^1) + ($40,000 / (1 + 0.14)^2) + ($50,000 / (1 + 0.14)^3) Project B: NPV = (-$100,000) + ($10,000 / (1 + 0.14)^1) + ($30,000 / (1 + 0.14)^2) + ($40,000 / (1 + 0.14)^3) + ($50,000 / (1 + 0.14)^4) + ($60,000 / (1 + 0.14)^5) + ($70,000 / (1 + 0.14)^6)
Based on the calculations, the NPV of Project A is $6,173.94 and the NPV of Project B is $5,953.72. Since the NPV of Project A is higher, I would recommend that the company accept Project A.