Final answer:
The project's Year 0 net cash flow is $1.93 million, Year 1 is $717,833.33, Year 2 is $717,833.33, and Year 3 is $1,497,833.33. The project's NPV, using a required return rate of 12%, is $1,647,811.59.
Step-by-step explanation:
The net cash flow for a project in Year 0 is the initial fixed asset investment minus the initial investment in net working capital. Therefore, the Year 0 net cash flow for this project is $2.18 million minus $250,000, which equals $1.93 million.
The net cash flow for Year 1 is the annual sales minus the costs, minus the depreciation expense for that year, plus the change in net working capital. Therefore, the Year 1 net cash flow for this project is $1.645 million minus $610,000, minus ($2.18 million divided by 3), plus ($250,000 minus ($2.18 million divided by 3)), which equals $717,833.33.
The net cash flow for Year 2 is calculated in the same way as Year 1. Therefore, the Year 2 net cash flow for this project is $1.645 million minus $610,000, minus ($2.18 million divided by 3), plus ($250,000 minus ($2.18 million divided by 3)), which equals $717,833.33.
The net cash flow for Year 3 is calculated in the same way as Year 1 and Year 2, with the exception that the fixed asset has a market value of $180,000 at the end of Year 3. Therefore, the Year 3 net cash flow for this project is $1.645 million minus $610,000, minus ($2.18 million divided by 3), plus ($250,000 minus ($2.18 million divided by 3)), plus ($180,000), which equals $1,497,833.33.
The project's NPV can be calculated by discounting the net cash flows at the required return rate (12%). The NPV is the sum of the present values of the net cash flows. Therefore, the NPV for this project is the present value of Year 0 net cash flow, plus the present value of Year 1 net cash flow, plus the present value of Year 2 net cash flow, plus the present value of Year 3 net cash flow. Using a financial calculator or spreadsheet, the NPV is $1,647,811.59.