Answer: $65,890
Step-by-step explanation:
When it comes to capitalizing fixed assets, every cost that was incurred to get the fixed asset ready for use will be included in the cost price.
The cost price here is therefore;
= Cost price + Sales taxes + Logo + safety testing
= 60,000 + 4,000 + 1,600 + 290
= $65,890