Answer:

60 man-days

Explanation:

Lets find a rate that will be in units of (man-days/job).

"5 men can complete half of work within 6 days" can be written mathematically as:

(5 men)*(6 days)/(0.5 job)

which reduces to: 30 man-days/0.5 job, or 60 man-days/job

The work in man days for a complete job would therefor be 60 man-days.