Using the following data, determine what the baseline,

entitlement, and target are.
Failure time on machine 2
150
155
152
123
110
90
92
89
90
210
223
230
219

User Orizon
by
7.5k points

1 Answer

6 votes

Answer:

Baseline is approximately equal to 143.69.

Entitlement is 89 and Target cannot be determined without any further information or specific criteria.

Step-by-step explanation:

Baseline = (150 + 155 + 152 + 123 + 110 + 90 + 92 + 89 + 90 + 210 + 223 + 230 + 219) / 13

Entitlement: Under ideal conditions, the entitlement represents the desired or expected performance level. It is frequently used as a reference point.

The goal is the intended level of performance that must be reached or maintained. It can be set based on a variety of variables such as industry standards, client expectations, or organisational goals. In this scenario, the objective may be a specified failure time on machine 2 that the organisation wishes to attain. However, without more information or precise criteria, we cannot determine the target from the supplied data.