50 men can built a 300m wall in 20 days . How many days will 25 men required to build a 60m wall

User Pervez
by
8.1k points

1 Answer

2 votes

SOLUTION:

First, we can use the formula:


  • \text{work} = \text{rate} * \text{time}

To solve for the rate, we can use:


  • \text{rate} = \frac{\text{work}}{\text{time}}

For the first scenario, we have:

  • 50 men
  • 300m wall
  • 20 days

We can use the formula to solve for their rate:


\text{rate}_1 = \frac{300\text{m}}{20\text{ days} * 50\text{ men}} = 0.3 \frac{\text{m}}{\text{day} \cdot \text{man}}

Now, let's solve for the time required for 25 men to build a 60m wall. We can use the rate from the first scenario to solve for the time:


\text{rate}_1 = \text{rate}_2


0.3 \frac{\text{m}}{\text{day} \cdot \text{man}} = \frac{60\text{m}}{\text{time} \cdot 25\text{ men}}


\text{time} = \frac{60\text{m}}{0.3 \frac{\text{m}}{\text{day} \cdot \text{man}} \cdot 25\text{ men}} = \boxed{8 \text{ days}}


\therefore 25 men can build a 60m wall in 8 days.


\blue{\overline{\qquad\qquad\qquad\qquad\qquad\qquad\qquad\qquad\qquad\qquad\qquad\qquad\qquad\qquad\qquad}}

User Samir Mangroliya
by
8.3k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories