Answer: Key Milestones
Explanation: The schedule section of a scoping document typically includes key milestones. These milestones outline important dates or events during the project that help track progress and ensure timely completion.
While it is not common to include payment schedule, hours of work per week, or taxes to be paid by the vendor in the schedule section of a scoping document, they may be included in other sections of the document such as the financial or contractual terms.
To summarize, the schedule section of a scoping document should primarily focus on key milestones.