Final answer:
The minimum project time for HQH's transition to a connected ERP database is 10 weeks.
Step-by-step explanation:
In order to determine the minimum project time for HQH's transition to a connected ERP database, we need to analyze the duration of each step and identify any dependencies between them. Based on the given information, the four main steps are:
- System Hardware Install: Setting up servers (2 weeks) and setting up in-store systems (3 weeks). These sub-steps can be done simultaneously, so the duration is the maximum of the two, which is 3 weeks.
- System Data Upload: This step takes 2 weeks.
- Limited System Test: This step can only happen if the first two steps are done and takes 3 weeks for the actual test and the diagnostics.
- Nationwide Systems Change-over: This step has two sub-steps - a 2-week implementation followed by a 2-week diagnostic period. The total duration for this step is 4 weeks.
To calculate the minimum project time, we need to consider the dependencies between the steps. The Limited System Test can only happen after the System Hardware Install and System Data Upload are completed, so its duration is added to the maximum duration of those two steps. Finally, the Nationwide Systems Change-over can only happen after the Limited System Test is completed, so its duration is added as well. Therefore, the minimum project time is:
Total = Maximum(System Hardware Install, System Data Upload) + Limited System Test + Nationwide Systems Change-over
Total = Maximum(3 weeks, 2 weeks) + 3 weeks + 4 weeks
Total = 3 weeks + 3 weeks + 4 weeks
Total = 10 weeks