Final answer:
To determine the project duration with only a 5% chance of time overrun using a PERT analysis with a duration variance of 2 weeks, the Z-value for a 95% confidence level is multiplied by the standard deviation and added to the mean duration, resulting in approximately 12.3 weeks.
Step-by-step explanation:
The PERT (Program Evaluation and Review Technique) analysis involves calculating the expected project duration and assessing the risk associated with meeting project deadlines. To find the project duration with a 5% chance of overrun, we can use the concept of standard deviation and the Z-value associated with a 95% confidence level (5% chance of overrun corresponds with the 95th percentile).
The Z-value for a 95% confidence level is approximately 1.645. Since the question states that the variance of the critical path duration is 2 weeks, we can calculate the standard deviation as the square root of the variance, which equals √2 or approximately 1.414 weeks.
To find the duration that has only a 5% chance to be exceeded, we multiply the Z-value by the standard deviation and add it to the expected duration:
Expected duration + (Z-value × Standard deviation) = 10 weeks + (1.645 × 1.414) = 10 weeks + 2.33 weeks ≈ 12.33 weeks
Therefore, the duration of the project that can be promised with only a 5% chance of time overrun is approximately 12.3 weeks.