98.1k views
5 votes
The​ three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1​ (they are​ parallel) before proceeding to station 2.

Station 1Machine A, Capacity: 30 units/hr,
Station 1Machine B,Capacity: 30 units/hr
Station 2 Capacity:5 units
Station 3 Capacity:6 units/hr
If the firm operates 9 hours per​ day, 5 days per​ week, the weekly capacity of this work cell is units​ (enter your response as a whole​ number).

User Richardo
by
7.6k points

2 Answers

6 votes

Final answer:

The weekly capacity of this work cell is 3570 units. To calculate it, we consider the capacity of each station and the firm's operating hours.

Step-by-step explanation:

To calculate the weekly capacity of this work cell, we need to consider the capacity of each station and the operating hours of the firm. Station 1 has two machines, Machine A and Machine B, each with a capacity of 30 units/hr. Since they are parallel, the total capacity of Station 1 is 60 units/hr. Station 2 has a capacity of 5 units, and Station 3 has a capacity of 6 units/hr.

To calculate the weekly capacity, we multiply the capacity of each station by the operating hours per day and the number of days per week. The formula is:

Weekly Capacity = (Station 1 capacity + Station 2 capacity + Station 3 capacity) x Operating hours per day x Number of days per week

Using the given information, we can calculate:

(60 units/hr + 5 units/hr + 6 units/hr) x 9 hours/day x 5 days/week = 3570 units per week

Therefore, the weekly capacity of this work cell is 3570 units.

User Joeycozza
by
8.1k points
5 votes

Final answer:

The weekly capacity of the work cell is determined by its bottleneck, which is Station 2 with a capacity of 5 units per hour. Multiplying this by the number of operating hours in a week (45 hours), we find that the weekly capacity is 225 units per week.

Step-by-step explanation:

To calculate the weekly capacity of the work cell, we first determine the bottleneck, which is the station with the lowest capacity. In this case, Station 2 with a capacity of 5 units per hour is the bottleneck. Because the other stations have higher capacities, they will be under-utilized, only able to produce as much as the bottleneck allows.

Since the firm operates 9 hours per day and 5 days per week, we multiply the capacity of the bottleneck (5 units/hr) by the number of operating hours in a week (9 hours/day * 5 days/week = 45 hours/week). Therefore, the weekly capacity equals 5 units/hr * 45 hours/week = 225 units per week.

User Denita
by
7.8k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories