Answer:
2 minutes/T-shirt
Step-by-step explanation:
The cycle time is the total amount of time it takes to produce one unit of a product. In this case, the factory has 400 minutes of effective productive time to produce 200 T-shirts. To calculate the cycle time, you can divide the total amount of productive time by the number of units produced:
Cycle time = Total productive time / Number of units produced Cycle time = 400 minutes / 200 T-shirts Cycle time = 2 minutes/T-shirt
So, in this factory, the cycle time allowed to produce a T-shirt is 2 minutes.