If Michelle takes 1 hour to complete 15

assignments, what is her productivity
rate?
A. 18.5
B. 15
C. 1.5
D. 7

1 Answer

1 vote

Answer:

15

Explanation:

productivity rate = output delivered / hours worked

according to the question

Michelle's productivity rate = 15 / 1

= 15