187k views
0 votes
Demonstrate a lras and sras model. label each curve correctly.

1 Answer

5 votes

To compute the total production cost per equivalent unit for work done during the period, we need to calculate the cost per equivalent unit for both direct materials and conversion costs separately.

First, let's calculate the cost per equivalent unit for direct materials:

Beginning work in process:

Units: 10,000

Percent completed: 90%

Direct Materials Costs: $10,000

Units started and completed during the period: 50,000

Ending work in process:

Units: 20,000

Percent completed: 30%

Total equivalent units for direct materials:

Beginning work in process: 10,000 units × 90% = 9,000 equivalent units

Units started and completed: 50,000 equivalent units

Ending work in process: 20,000 units × 30% = 6,000 equivalent units

Total equivalent units for direct materials = 9,000 + 50,000 + 6,000 = 65,000 equivalent units

Total direct materials costs = $10,000 + $110,000 (costs added this period) = $120,000

Cost per equivalent unit for direct materials = Total direct materials costs / Total equivalent units for direct materials = $120,000 / 65,000 equivalent units

Next, let's calculate the cost per equivalent unit for conversion costs:

Beginning work in process:

Units: 10,000

Percent completed: 90%

Conversion Costs: $30,000

Units started and completed during the period: 50,000

Ending work in process:

Units: 20,000

Percent completed: 30%

Total equivalent units for conversion costs:

Beginning work in process: 10,000 units × 90% = 9,000 equivalent units

Units started and completed: 50,000 equivalent units

Ending work in process: 20,000 units × 30% = 6,000 equivalent units

Total equivalent units for conversion costs = 9,000 + 50,000 + 6,000 = 65,000 equivalent units

Total conversion costs = $30,000 + $200,000 (costs added this period) = $230,000

Cost per equivalent unit for conversion costs = Total conversion costs / Total equivalent units for conversion costs = $230,000 / 65,000 equivalent units

Therefore, the computed total production cost per equivalent unit for work done during the period is as follows:

Cost per equivalent unit for direct materials = $120,000 / 65,000 equivalent units

Cost per equivalent unit for conversion costs = $230,000 / 65,000 equivalent units

User Dcgenjin
by
8.3k points