Answer:
a) It would have taken 1 person 14 days to do this amount of work.
b) It would take 1 person 56 days to finish building this house extension.
We know that 1 person can build a house extension in 70 days. This means that in 1 day, 1 person can do 1/70 of the work. In 7 days, 2 people can do 2 * 7 * 1/70 = 2/10 of the work. This means that 1 person can do 1/10 of the work in 7 days. To finish the remaining 8/10 of the work, 1 person would need 7 * 8 = 56 days.