17 Select the correct answer. Which task of the software planning process refers to scheduling the planned tasks and submitting the project plan to the customer for approval? A. validating the technology B. closing the planning phase C. developing project plans D. creating project schedules E. conducting risk management

1 Answer

5 votes

Answer:

The correct answer is D. creating project schedules.

Step-by-step explanation:

Creating project schedules refers to the task of scheduling the planned tasks and activities in the project plan. This involves breaking down the project into smaller tasks, estimating the time and resources required for each task, and creating a timeline or schedule for completing the tasks. Once the project schedule is developed, it is submitted to the customer or stakeholders for approval. This helps ensure that everyone is aligned on the timeline and expectations for the project delivery.