Answer:
The expected value in this situation can be calculated as follows:
E(X) = P(X) * V(X), where X is the random variable representing the profit of the construction company, P(X) is the probability of X, and V(X) is the value of X.
In this case, the profit of the construction company if the bid is accepted is $96,000 - $1,100 = $94,900, and the probability of the bid being accepted is 1/10. Therefore, we have:
E(X) = (1/10) * $94,900 = $9,490
The expected value of $9,490 means that in the long run, the construction company would expect to earn this amount on average per bid. Therefore, the correct answer is option A: "In the long run, the construction company would expect to earn this amount on average per bid."