How many days with 9 workers

How many days with 9 workers-example-1
User Vaqifrv
by
7.9k points

1 Answer

5 votes

Answer: 9.66666667

Explanation:

To find the number of days it would take to build a similar house, we would need to create a proportion.

Workers: 27:9

Days: 29:?

Let's simplify.

Workers: 3:1

Days: 29:?

Now, we divide 29 by 3 to see how many days it would take to build a similar house.

29/3=9.666666667 (9.6 repeating)

So, your answer would be 9.6