What earned value management (EVM) variable captures cost variance?

1 Answer

3 votes

Answer:

The cost variance is captured by the EVM variable known as CV, which measures the difference between the earned value and actual cost of work performed. This variable is a key indicator of project performance and can help identify areas where corrective action may be needed to keep the project on track.