A construction company is repaving 27 miles of a road. They can repave 2.4 miles per day.

How many days, to the nearest hundredth, will it take the company to repave the road?

1 Answer

1 vote

Answer:

It would take the company 11.25 days to repave the road.

Explanation:

27 miles to repave total

2.4 repavement per day

27 / 2.4 = 11.25

Therefore, it would take the company 11.25 days to repave the road.