Answer:
a) throughput time is the sum of inspection + process + move + queue = 0.5 + 2.8 + 0.7 + 4.5 = 8.5 days
b) manufacturing cycle efficiency = process time / throughput time = 2.8 / 8.5 = 33%
c) percentage of the throughput time for non-value added activities = 1 - 33% = 67%
d) new throughput time = 4 days
MCE = 2.8 / 4 = 70%