We can compute the expected value using the given values in the problem such as we have the cost of drawing and submitting the model amounting of $11,000.
We also know that once the project is awarded to them, the anticipated profit is $180,000. Therefore, the expected value is just $180,000 minus $55,000 and the answer is $125,000.