Time between completions"" is the fundamental basis of a capacity calculation True/False?

User Hyarion
by
8.2k points

1 Answer

4 votes

Answer: false

Step-by-step explanation:

"Time between completions" is not the fundamental basis of a capacity calculation. The fundamental basis of a capacity calculation is the maximum amount of output that a system can produce in a given period of time, taking into account limitations such as resources, technology, and efficiency.