This project would cost $27,000 (option B) to the contractor for a building size of 900ft.
Given = 240 ft take 72 hours:
240 ft / 72 hours = 900 ft / x hours
Cross-multiplying, we get:
240 ft x x hours = 72 hours x 900 ft
x = (72 hours x 900 ft) / 240 ft
x = 270 hours
So, for a 900 ft project, it would take 270 hours of work.
The cost of the project can be found by multiplying the number of hours by the labor cost per hour:
Cost = hours x labor cost per hour
Cost = 270 hours x $100 per hour
Cost = $27,000