Answer:
Step-by-step explanation:
Expenditures: This refers to the amount of money that has been spent on the project up to a particular point in time, such as week 24.
Earned Value: This is the value of the work that has been completed on the project up to a particular point in time, expressed in dollars. It represents the amount of the budget that has been earned by completing work on schedule.
Actual Expenses: This is the actual amount of money that has been spent on the project up to a particular point in time, such as week 24.
Cost Variance (CV): This is the difference between the earned value and the actual expenses. A positive value means that the project is under budget, while a negative value means that the project is over budget.
Schedule Variance (SV): This is the difference between the earned value and the planned value (the budgeted cost of the work scheduled to be completed). A positive value means that the project is ahead of schedule, while a negative value means that the project is behind schedule.
Cost Performance Index (CPI): This is the ratio of earned value to actual expenses. A value greater than 1 means that the project is under budget, while a value less than 1 means that the project is over budget.
Schedule Performance Index (SPI): This is the ratio of earned value to planned value. A value greater than 1 means that the project is ahead of schedule, while a value less than 1 means that the project is behind schedule.
Estimate to Complete (ETC): This is an estimate of the cost of completing the remaining work on the project, based on the performance to date.
Estimate at Completion (EAC): This is an estimate of the total cost of the project, based on the performance to date and the estimate to complete.