Carol is ordering bricks for two large construction jobs at the same location. The first job needs 500 bricks every day for 9 days and the second job needs 700 bricks every day for 9 days. What is the total number of bricks Carol needs for both jobs?​

User Shylajhaa
by
2.8k points

1 Answer

18 votes
18 votes

Answer:

10,800

Explanation:

500 X 9 = 4,500

700 X 9 = 6,300

4,500 + 6,300 = 10,800

The total number of bricks Carol needs for both jobs is 10,800.