Dear Marlon and Alana,
I have received a request from Clark regarding Structionsite photos of areas just prior to return air TAB. According to the attached email from Clark, the NL1/NL2 return air TAB will begin on Tuesday, 4/4. Although the cleanliness of these floors is satisfactory, we want to document the cleanliness of the floors before pulling return air. If the areas look good, we might be able to proceed without any further action.
We are considering a site walk, but we wanted to inform you in advance in case you need to be present. Could you please confirm if you can be on site on Tuesday morning to take photos if necessary? Your thoughts on this matter would be appreciated.
Thank you.