Chapter 8 discusses the use of PERT (program evaluation and review technique.) below the steps of the manufacturing process (page 118 of the chapter):

Analyze the task to complete a given project.
Estimate the time needed to complete each task
compute the minimum time needed to complete the whole project
identifying the critical path


Requirements:

1. You must post a discussion thread highlighting your thoughts on the topic and addressing the questions below.

Discussion Topics:

1. Discuss as a business owner how would you analyze and sequence tasks that need to happen for your manufacturing toy company.

2. Discuss how you would implement PERT process into your company.

3. Discuss how you would identify a critical path and correct it for the future

User Roya
by
8.4k points

1 Answer

5 votes
1. As a business owner of a manufacturing toy company, I would analyze and sequence tasks that need to happen by breaking down the manufacturing process into smaller, more manageable tasks. This can be done by creating a flowchart or process map that outlines the steps involved in each stage of production, from design and development to packaging and shipping. Once each task has been identified, I would estimate the time needed to complete each task based on previous production data, employee expertise, and other relevant factors.

2. To implement the PERT process into my company, I would use a project management software or tool that can help me analyze and evaluate the tasks involved in the manufacturing process. I would input the estimated time for each task into the software, and it would automatically compute the minimum time needed to complete the whole project and identify the critical path. This would allow me to better manage my resources and allocate them efficiently to complete the project on time and within budget.

3. To identify a critical path and correct it for the future, I would review the PERT diagram and identify the sequence of tasks that have the longest duration and the least amount of scheduling flexibility. These tasks are critical to the success of the project, and any delays in completing them could cause a delay in the overall project completion. To correct the critical path, I would focus on improving the efficiency of these tasks by using better tools, techniques or allocating more resources to complete them in a shorter period. This would help me to reduce the duration of the critical path, making the entire project easier to manage and complete on time.
User Tom Wright
by
8.9k points