A road crew can repave 1/30 miles of road each hour. They must repave a road that is 2/5 miles long. How long will it take the crew to repave the road? Write your answer in simplest form.
asked
Mar 14, 2024
118k
views
5
votes
A road crew can repave 1/30 miles of road each hour. They must repave a road that is 2/5 miles long. How long will it take the crew to repave the road?
Write your answer in simplest form.
Mathematics
middle-school
Daniel Rafael Wosch
asked
by
Daniel Rafael Wosch
7.9k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
2
votes
The quality is true and it’s 25 I think
Dejavu
answered
Mar 17, 2024
by
Dejavu
8.2k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
5
votes
Answer: 12 hours
Total length of road: 2miles/5
Amount repaved per hour: 1/30
Solving using the unitary method:
Cully
answered
Mar 21, 2024
by
Cully
8.2k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.3m
questions
12.0m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org