186k views
4 votes
A project has four activities that take 4, 3, 6, and 7 days respectively. What is the total completion time for the project?

3 days, as this is the minimum time
7 days, as this is the maximum time
20 days, as this is the sum of the times
It is not possible to determine the total completion
time from the given information

2 Answers

2 votes

Answer:

20 days

Explanation:

To find the total time, we will just add up the days.

4 + 3 + 6 + 7 = 20 days.

User Artur Gaspar
by
8.2k points
3 votes

Answer:

(d) not possible to tell from information given

Explanation:

You want to know the total completion time for a project with four activities that take 4, 3, 6, and 7 days.

Completion time

The project completion time will be determined by the dependencies between activities.

Series

If each activity must be completed before the next, then the total time will be 4+3+6+7 = 20 days.

Parallel

If there are no dependencies and all activities can be done in parallel, then the total completion time is 7 days, the time required for the longest activity.

In short, it is not possible to determine the total time from the information given.

User SubmarineX
by
8.1k points

No related questions found