Can anyone help :)

all ik is the answer is not 80

Can anyone help :) all ik is the answer is not 80-example-1
User Jmgross
by
7.6k points

1 Answer

0 votes
Answer is 95
Explanation:
Both can run at the same time
Processor 1 would be doing task A C making the time 80
Processor 2 would be doing task B D making the time 95
Both have to finish in order to complete all four task meaning the minimum time would be 95