Final answer:
The team's average velocity is 9.2 story points per sprint, indicating their typical workload capacity during Agile project management.
Step-by-step explanation:
The velocity of a team in Agile methodologies, such as Scrum, is a measure of the amount of work they can complete in a single sprint. Based on the information provided, the team's average velocity is calculated as 9.2 story points per sprint. This figure is derived from the team's performance over the past year and indicates the average amount of work in story points that the team can handle in each sprint cycle.
Velocity is a critical factor in Agile planning and management as it helps in predicting how much work the team can accomplish in future sprints and aids in the scheduling and assignment of tasks. It is important to consider that while velocity can be a useful indicator of a team's capabilities, it is not a measure of the team's quality or value delivery, and it should not be used to compare different teams.