Final answer:
The Gantt chart is not a typical artifact of the Scrum framework because Scrum promotes adaptability and flexibility, which is contrary to the fixed plan nature of a Gantt chart.
Step-by-step explanation:
The Gantt chart is NOT a typical artifact of the Scrum framework. Scrum is an agile methodology for project management and software development, which emphasizes flexibility, collaboration, and customer feedback. The three primary artifacts in Scrum are:
Product Backlog - a prioritized list of features, functions, requirements, enhancements, and fixes that serve as a 'to-do' list for the project.
Sprint Backlog - a list of tasks and work to be done during the Sprint, which is a time-boxed interval meant for a specific set of work to be completed.
Burn down Chart - a visual measurement tool that displays the work done versus the work remaining in a Sprint on a daily basis.
The Gantt chart, a traditional project management tool that displays activities along a timeline, is not commonly used in Scrum because it represents a fixed plan which contradicts Scrum's adaptability.