During Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. What are the two most appropriate responses for the Scrum Master?

A) Accept the proposal
B) Reject the proposal
C) Facilitate a discussion
D) Implement the change immediately

User Keely
by
8.7k points

1 Answer

1 vote

Final answer:

The correct responses for the Scrum Master would be to facilitate a discussion about the proposed change in Daily Scrum frequency (C) and, if there is a consensus, to implement the change (D).

Therefore, the correct options are:

C) Facilitate a discussion

D) Implement the change immediately.

Step-by-step explanation:

The Scrum Master's role is to ensure that the Scrum process is followed while also being a servant-leader to the team.

Therefore, the correct approach would be to facilitate a discussion to understand the reasons behind the team's proposal and to gauge the potential impact on the project's progress.

It's important to note that the Daily Scrum serves as a key inspect-and-adapt meeting to synchronize activities and create a plan for the next 24 hours.

Altering its frequency could affect the team's performance and should be carefully considered. The Scrum Master should ensure that any decisions made are in the team's best interest and do not conflict with the fundamental principles of Scrum.