A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?

a) Ignore the logistical challenges; they are not relevant to Scrum
b) Facilitate communication and ensure that the team can effectively participate in the Daily Scrum
c) Suggest canceling the Daily Scrum since it is too difficult to coordinate
d) Ask the team to handle the logistics themselves

User Adris
by
8.1k points

1 Answer

4 votes

Final answer:

The Scrum Master should facilitate communication and assist with logistical challenges to ensure effective participation in the Daily Scrum for a distributed Development Team.

Step-by-step explanation:

A Scrum Master is tasked with facilitating the Scrum process and removing impediments that may prevent a team from being productive. In the scenario where a Development Team is distributed across different locations, creating logistical challenges for the Daily Scrum, the Scrum Master should take action to facilitate communication and ensure that the team can effectively participate in the Daily Scrum. This may involve helping to set up conference calls or finding tools that better support the team's communication needs. It's important for the Scrum Master to help alleviate these logistical hurdles so the team can focus on the work at hand.