How long does a Scrum cycle, also known as a Sprint, typically last?

A) 1-2 weeks
B) 3-4 months
C) 6-8 weeks
D) 9-12 months

User David Lyod
by
8.6k points

1 Answer

5 votes

Final answer:

The typical duration of a Scrum cycle, or Sprint, is 1-2 weeks. However, the duration can vary depending on the needs of the project or organization.

Step-by-step explanation:

The typical duration of a Scrum cycle, or Sprint, in the Scrum framework is 1-2 weeks. A Sprint is a time-boxed iteration during which a Scrum team completes a set of planned work. It is important to note that the duration of a Sprint can vary depending on the specific needs and circumstances of a project or organization. For example, some teams might choose to have longer Sprints of 3-4 weeks, while others might have shorter Sprints of 1 week. The key is to find a balance that allows for regular delivery of value without sacrificing quality.