The phase setting for a demolition view is new construction. (T/F)

1 Answer

5 votes

Final answer:

The phase setting for a demolition view is typically false to be new construction, as demolition usually precedes new construction and represents a distinct phase.

Step-by-step explanation:

The statement that the phase setting for a demolition view is new construction is typically false. Within the context of architectural designs or construction documents, phases represent different periods or stages within the lifecycle of a building project. The demolition phase often precedes the new construction phase, because it involves the removal of existing structures or components before new construction can commence. Therefore, the phase setting for a demolition view would logically be 'Demolition' rather than 'New Construction'.