__________ the air-conditioning system before any repair or nitrogen testing, is required by the Environmental Protection Agency (EPA).

a) Leak testing
b) Reclaiming
c) Charging
d) Evacuation

1 Answer

3 votes

Final answer:

The correct answer is option d) Evacuation. Before any repair or nitrogen testing, the Environmental Protection Agency (EPA) requires the air-conditioning system to be evacuated.

Step-by-step explanation:

The correct answer is option d) Evacuation.

Before any repair or nitrogen testing, the Environmental Protection Agency (EPA) requires the air-conditioning system to be evacuated. Evacuation involves removing all moisture, air, and contaminants from the system using a vacuum pump. This process ensures that the system is ready for further maintenance or testing.

The correct answer is option d) Evacuation. As per the United States Environmental Protection Agency (EPA) regulations, evacuation of the air-conditioning system is necessary before any repair work or nitrogen testing can be conducted.

This process involves removing any refrigerants from the system to prevent them from escaping into the atmosphere, which could contribute to environmental harm, such as ozone depletion or global warming. The EPA guidelines are strict due to the harmful effects of some refrigerants on the environment.

Therefore, technicians are required to use a recovery machine to capture these substances under vacuum, ensuring they are properly handled and disposed of or reclaimed for future use.