12.6k views
1 vote
At the end of the watch the deck log should be signed by which of the following personnel people?

a.Option 1: Commanding Officer
b.Option 2: Chief Engineer
C.Option 3: Junior Seaman
D.Option 4: Cook

User Thyzz
by
7.0k points

1 Answer

4 votes

Final answer:

At the end of the watch, the deck log should be signed by the Commanding Officer and the Chief Engineer.

Step-by-step explanation:

At the end of the watch, the deck log should be signed by the Commanding Officer and the Chief Engineer.

User ThibThib
by
7.4k points