118k views
0 votes
"A project consists of 150 jobs. The expected completion time for each job is given in days. The project has three critical paths with two jobs in common, J and K. In order to finish the project one day early, the completion time should be reduced one day for

a) each of the 150 jobs
b) each of the jobs on the three critical paths
c) either Job J or Job K
d) both Job J and Job K"

1 Answer

5 votes

Final answer:

To finish the project one day early, the completion time should be reduced by one day for each of the 150 jobs.

Step-by-step explanation:

To finish the project one day early, the completion time should be reduced by one day for each of the 150 jobs. This means that the expected completion time for each job should be decreased by one day.

So, the correct answer is (a) each of the 150 jobs.

User Nikk Wong
by
8.0k points