What is the logical relationship that exists between the project tasks or between a project task and a milestone?

o resource
o dependency
o task
o activity

User Dlackty
by
7.9k points

1 Answer

2 votes

Final answer:

The logical relationship between project tasks or between a project task and a milestone is called a dependency.

Step-by-step explanation:

The logical relationship that exists between project tasks or between a project task and a milestone is called a dependency. A dependency represents a sequence or order of tasks in a project, where one task depends on the completion of another. It ensures that tasks are performed in a specific order to maintain project flow and achieve project objectives.

For example, if you have a project task of designing a website, you may have a dependency on the completion of a task for gathering client requirements. The website design task cannot start until the client requirements are gathered. This dependency ensures that the website design task is not conducted prematurely.

User Cheslijones